Project Schedule

Gantt — Workstreams, Milestones & Dependencies

14 workstreams over 80 weeks · phased pilot-to-portfolio rollout.

Complete
In Progress
Planned
Milestone
Dependency
StartWk 4Wk 8Wk 12Wk 16Wk 20Wk 24Wk 28Wk 32Wk 36Wk 40Wk 44Wk 48Wk 52Wk 56Wk 60Wk 64Wk 68Wk 72Wk 76Wk 80Feasibility & Site AssessmentEngineering6wGrid Connection & TAOZ RegistrationRegulatory11wEPC Procurement & TenderingProcurement11wFinancial CloseDetailed Engineering DesignEngineering13wPermitting & Regulatory ApprovalRegulatory13wSolar PV InstallationEPC21wFirst Site EnergizedBESS InstallationEPC19wModular DC ConstructionEPC23wV2G Fleet Procurement & ChargingFleet Ops21wGrid Interconnection & CommissioningEPC11wFull VPP OperationalDC Tenant OnboardingCommercial11wVPP Optimization & NOGA MSP IntegrationOperations13wPerformance Testing & HandoverEngineering11w10-Site Portfolio Rollout (Phase 2)Program Office19wPortfolio Complete
WorkstreamOwnerStartDurationEndDependenciesStatusMilestone
Feasibility & Site AssessmentEngineeringWk 16wWk 7—Complete—
Grid Connection & TAOZ RegistrationRegulatoryWk 411wWk 15Feasibility & Site AssessmentIn Progress—
EPC Procurement & TenderingProcurementWk 811wWk 19Feasibility & Site AssessmentIn ProgressFinancial Close
Detailed Engineering DesignEngineeringWk 1013wWk 23Feasibility & Site Assessment, EPC Procurement & TenderingPlanned—
Permitting & Regulatory ApprovalRegulatoryWk 1213wWk 25Grid Connection & TAOZ RegistrationPlanned—
Solar PV InstallationEPCWk 2021wWk 41Detailed Engineering Design, Permitting & Regulatory ApprovalPlannedFirst Site Energized
BESS InstallationEPCWk 2419wWk 43Detailed Engineering Design, Permitting & Regulatory ApprovalPlanned—
Modular DC ConstructionEPCWk 2223wWk 45Detailed Engineering DesignPlanned—
V2G Fleet Procurement & ChargingFleet OpsWk 2621wWk 47Detailed Engineering DesignPlanned—
Grid Interconnection & CommissioningEPCWk 4011wWk 51Solar PV Installation, BESS InstallationPlannedFull VPP Operational
DC Tenant OnboardingCommercialWk 4411wWk 55Modular DC Construction, Grid Interconnection & CommissioningPlanned—
VPP Optimization & NOGA MSP IntegrationOperationsWk 4813wWk 61Grid Interconnection & CommissioningPlanned—
Performance Testing & HandoverEngineeringWk 5611wWk 67VPP Optimization & NOGA MSP IntegrationPlanned—
10-Site Portfolio Rollout (Phase 2)Program OfficeWk 6019wWk 79Performance Testing & HandoverPlannedPortfolio Complete