Flying Cargo · Energy Sovereignty
Executive Energy Modeler
Project Development

Origination → Commercial Operation Date

Full development lifecycle: 10 phases, 10 stage gates, 80-week critical path to COD.

Critical Path
80 weeks
~1.5 years to portfolio complete
COD Target
Week 60
First site energized + grid sync
Dev Budget
₪270.7M
100.0% of CAPEX
Phases Complete
2/10
20.0%
Development Timeline & Stage Gates
W0W20W40W60W80Origination & StrategyFeasibility & Site AssessmentLand & Lease AgreementsGrid Connection & TAOZ RegistrationPermitting & Regulatory ApprovalDetailed Engineering DesignEPC Procurement & TenderingConstruction & InstallationCommissioning & Grid InterconnectionOperations & OptimizationCOD
Development Budget Allocation
Pre-Development7.0% · ₪18.9M
Development18.0% · ₪48.7M
Execution63.0% · ₪170.5M
Operations12.0% · ₪32.5M
Stage Gates
Board Mandate
Week 4 · Business Development
Go/No-Go Decision
Week 12 · Engineering
Site Control
Week 18 · Legal & Real Estate
Grid Connection Agreement
Week 26 · Regulatory
Permit Set Complete
Week 32 · Regulatory
Issued for Construction (IFC)
Week 30 · Engineering (EPC)
Financial Close
Week 30 · Procurement
Mechanical Completion
Week 54 · EPC Contractor
Commercial Operation Date (COD)
Week 60 · EPC + IEC
Portfolio Complete
Week 80 · Operations (O&M)
Phase Detail
PhaseCategoryOwnerWeeksBudget %GateStatus
Origination & Strategy
Identify opportunity, align with corporate strategy, secure board mandate for pilot expansion.
Pre-DevelopmentBusiness Development0–41.5%Board MandateComplete
Feasibility & Site Assessment
Site walks, load profile analysis, interconnection screening, solar/BESS sizing, go/no-go.
Pre-DevelopmentEngineering4–123.0%Go/No-Go DecisionComplete
Land & Lease Agreements
Negotiate rooftop/ground leases, easements, and site access rights with facility owners.
Pre-DevelopmentLegal & Real Estate8–182.5%Site ControlIn Progress
Grid Connection & TAOZ Registration
IEC connection application, grid impact study, TAOZ tariff registration, NOGA MSP enrollment.
DevelopmentRegulatory10–264.0%Grid Connection AgreementIn Progress
Permitting & Regulatory Approval
Building permits, environmental approvals, fire safety, local authority licenses.
DevelopmentRegulatory14–325.0%Permit Set CompletePlanned
Detailed Engineering Design
Single-line diagrams, civil/structural, electrical, SCADA, V2G integration design.
DevelopmentEngineering (EPC)16–306.0%Issued for Construction (IFC)Planned
EPC Procurement & Tendering
Tender EPC scope, negotiate supply agreements for PV/BESS/DC/V2G, financial close.
DevelopmentProcurement18–303.0%Financial ClosePlanned
Construction & Installation
Civil works, mechanical installation, electrical, BESS commissioning, DC build-out.
ExecutionEPC Contractor30–5455.0%Mechanical CompletionPlanned
Commissioning & Grid Interconnection
Energization, performance testing, grid sync, VPP/EMS integration, NOGA MSP go-live.
ExecutionEPC + IEC52–608.0%Commercial Operation Date (COD)Planned
Operations & Optimization
O&M, arbitrage optimization, V2G dispatch tuning, tenant onboarding, phase-2 rollout.
OperationsOperations (O&M)60–8012.0%Portfolio CompletePlanned
Key Deliverables by Phase
Origination & Strategy
  • Opportunity memo
  • Board resolution
  • Budget envelope approval
Feasibility & Site Assessment
  • Feasibility study
  • Load profile report
  • Interconnection pre-screen
Land & Lease Agreements
  • Lease agreements
  • Easement rights
  • Access agreements
Grid Connection & TAOZ Registration
  • IEC connection offer
  • Grid impact study
  • TAOZ registration certificate
Permitting & Regulatory Approval
  • Building permit
  • Environmental approval
  • Fire safety sign-off
  • Business license
Detailed Engineering Design
  • IFC drawing set
  • BOM finalized
  • SCADA architecture
EPC Procurement & Tendering
  • EPC contract
  • Equipment supply agreements
  • Financial close memo
Construction & Installation
  • Civil works complete
  • PV/BESS installed
  • DC containers set
Commissioning & Grid Interconnection
  • Energization certificate
  • Performance test report
  • VPP live signal
Operations & Optimization
  • O&M handover
  • Optimization playbook
  • Phase-2 plan